 |
|
|
 |
Snowflake
White Mountain Power |
|
| |
|
|
| |
In 2006, NZ Legacy, LLC begin construction on a 24MW electrical
generation biomass plant, Snowflake White Mountain Power
(SWMP) near Snowflake, Arizona.
In November 2007, NZ Legacy, LLC merged it's biomass operations: Renegy, LLC with Catalytica Energy Systems Inc., to form a new company: Renegy Holdings, Inc. ("Renegy"). Renegy owns and operates SWMP.
The $53 million plant
started commercial operation June 2008, to meet the
power obligations under its 20-year Power Purchase Agreements
with Arizona Public Services (APS) and Salt River Project
(SRP). |
|
| |
|
|
| |
The plant was built at the Catalyst Paper Mill (formerly Abitibi) twelve miles west of Snowflake, AZ. |
|
| |
|
|
| |
Plant Facts and History: |
|
| |
|
|
| |
On September 27, 2004, SRP notified SWMP that SWMP’s
bid was selected as the result of their RFP to purchase
10MW of biomass produced power. Negotiations with SRP
were quickly completed and a 20-year PPA was signed.
SRP takes 10MW of the power for the first 15 years
of the contract and the full 20MW of production for
the following five years. |
|
| |
|
|
| |
APS agreed to take another 10 MW of biomass
generated power from the plant and signed a PPA
to purchase this power for 15 years. |
|
| |
|
|
| |
Both PPAs have price escalators in place for the
life of the agreements. |
|
| |
|
|
| |
The plant was built with a new Babcock and Wilcox
bubbling fluidized bed boiler built specifically
to meet the fuel makeup at SWMP. The plant’s economics
were improved by taking advantage of an idled paper
facility in Houston, Texas from where much of the SWMP
plant’s other components (conveyors, screw presses,
etc.) were acquired. |
|
| |
|
|
| |
Fuel for the biomass plant comes from two main
sources. First, is woody waste material from the
surrounding National Forests. Renegy harvests and provides fuel from green
forest thinning activities, forest rehabilitation work
on the burn area of the Rodeo-Chediski fire area and
waste material from the region’s existing saw
mills. Secondly, the Catalyst paper mill, produces 250 bone dry tons of waste recycled
paper fibers each day which are currently sent to an
adjoining landfill. These paper fibers are now sent
through an additional pressing facility to lower their
moisture content and become additional fuel for
the SWMP boiler. |
|
| |
|
|
| |
Benefits of locating the biomass
facility at Catalyst paper mill include: |
|
| |
|
|
| |
• |
69KV dedicated line to APS’s Cholla Power
Plant, the preferred delivery point for SRP’s
power. Without further upgrades the line can take
at least 25 MW of additional electricity to Cholla.
The transmission agreement is already in place. |
|
|
• |
APS has confirmed that the White Mountain communities
of Showlow, Pinetop, Lakeside, Heber, Snowflake,
etc. all use this feeder line and it is overloaded
from Cholla to the White Mountain area. By placing
a generating source at Catalyst, this bottleneck
is relieved for about 5 years and APS is greatly
benefited. It is conceivable that much more power
could be generated and delivered from this site
due to the growth in the local market. |
|
|
• |
Enough paper sludge to power a 6 MW power plant
annually with no other feedstock on a go forward
basis without touching the 720,000 tons in a landfill
today. The landfill also serves as a place to
dump ash from the biomass boilers. |
|
|
• |
Natural Gas is already available to the site for
startup and if needed for drying feedstock, etc. |
|
|
• |
State-of-the-art control room and monitoring equipment
allows Renegy to more closely monitor power quality. |
|
|
• |
Up-time guarantee exceeds the SRP and APS
PPA levels of compliance of 90%. |
|
|
• |
Land is available with plenty of space to work
including a fire protected chip yard that was previously
used for 35 years as the location to store chips. |
|
|
• |
ADEQ certified engineers test
air quality for compliance 24X7. |
|
|
• |
Boiler feed water supply is available with treatment
for the highest pressure boilers. |
|
|
• |
Catalyst has company-owned rail service (Apache
Railway), trucking contracts with Swift Trucking,
truck traffic control, scaling facilities and personnel,
security, maintenance (certified power plant mechanics,
welders, etc.), spare parts warehousing, fire suppression
teams, human resources, accounting, office space,
management, abandoned chip yard and associated assets,
etc. |
|
|
|
For more information about Renegy Holdings, Inc. |
|
|
|
|
|
| |
|
|
| |
|
|
| |
Snowflake
White Mountain Power Biomass Plant Makes Headlines |
|
 |
|
 |
| |
Energy
Services Bulletin Discusses
SWMP Project (Read
More) |
|
| |
|
|
| |
Arizona
Department of Commerce Authorized $39.25 Million in
Bonds (Read
More) |
|
| |
|
|
| |
Navajo
County and City of Show Low
Authorize SWMP Bonds (Read
More) |
|
| |
|
|
| |
SRP
Buys Biomass Power
from SWMP (Read
More) |
|
| |
|
|
| |
|
|
| |
|
|
| |
Early
Support for USDA and
Environmental Groups (Read
More) |
|
| |
|
|
| |
Important
Documents |
|
| |
|
|
| |
|
|
| |
|
|
| |
Biomass
Industry News |
|
| |
|
|
| |
Experts
Ponder Future of Biomass:
Power Magazine - May 2007
|
|
| |
5/07 - Experts discuss important trends
and success factors for the biomass industry.
(See
full article) |
|
| |
|
|
| |
Four
Major States Order
Increased Purchase of Bio Fuels
|
|
| |
11/05 - Governors in New York, Texas,
Wisconsin and Minnesota order state agencies to save energy
and increase their purchase and use of bio-fuels. (See
full article) |
|
| |
|
|
| |
$200
Million In Loan Guarantees Set
Aside For Biomass Energy Projects |
|
| |
7/05 - The USDA's Rural Development
Renewable Energy Program decides to set aside $200 million
in loan guarantees for biomass energy projects. (See
full article) |
|
| |
|
|
| |
Biomass
Educational Resources |
|
| |
|
|
|
What
is biomass and how is it used as an energy resource? To
find out more, Click
Here |
|
| |
|
|
| |
|
|
|